IMPORTANT NOTICE:Aquatic Center Emergency Leak Repair Update
Dear St. Francis Community,
There is a significant leak in either the supply or return shower lines in the aquatic center, with water draining into the parking lot in front of the building. To repair the cracked/leaking line, both a mason and a plumber will be required.
The mason will first saw-cut into the pool deck along the eastern side near the mechanical room. The plumber will then excavate beneath the concrete, locate the damaged pipe, and complete the repair.
The pool deck opening will remain exposed for approximately two days to ensure the repair is holding and that no additional leaks are present. Once the plumbing work is confirmed to be complete, the mason will return to close and restore the deck.
The total duration of the project is expected to be about five days. The pool facility can remain open during the plumbing work, but will need to close during the masonry work (saw cutting/drilling).
We are hopeful the contractors can begin this emergency repair next week (no start as of Friday 5/8). We are coordinating contractors and once we know the start date of the repair schedule it will be re-communicated with any new updates.
Kevin Walsh
Executive Director